Planning Poker - Agile Estimation


A consensus based estimation technique mainly used in agile environment. It can be used to estimate days or story points for any requirement.


Equipment needed:

  • A deck of cards: Cards in the deck have numbers on them. A typical deck has cards showing the Fibonacci sequence including a zero: 0, 1, 2, 3, 5, 8, 13, 21, 34, 55, and 89.
  • Requirement list (which need to be estimated


How to apply:

  • A Moderator, who normally doesn’t play, chairs the meeting.
  • The Product Owner provides a short overview of the user story. The team is given an opportunity to ask questions and discuss to clarify assumptions and risks.
  • Each individual lays a card face down representing his/her estimate instead of speaking them aloud.
  • Everyone calls their cards simultaneously by turning them over.
  • People with high estimates and low estimates has given the opportunity to justify their estimate and then discussion continues.
  • This estimation process is repeated until a consensus is reached for a particular feature and then it is repeated for next requirement item